Overtime % practice

Work out how much extra time a project team is working: the overtime hours divided by the team’s regular hours (people × regular hours each), times 100. Divide by the regular hours only, never by a total that already includes the overtime. Your answer marks itself as you type: a tick when it is right, a cross when it needs another look. Stuck? Open the working.

Example 1
0 of 1 correct

Type the overtime as a percentage of regular hours to 2 decimals (for example X or X.00). The box turns green when it is correct.

Your answer is correct

Well done. Try another example to make sure it sticks, or see how Praxis Practice™ can take you further.